#18: Going after the big fish

Overview
Start Date: 02/07/2009 End Date: 02/27/2009
13 items with a total relative size of 69 points
DONE tickets (69 points): 13
Sized tickets (0 points): 0
Partially Sized tickets (0 points): 0
Unsized tickets (0 points): 0
/ Total tickets (69 points): 13
agile-trac.org
agiletrac patch to core
agiletracplugin
completion stages
iterations
roadmap UI customisation
Value
Id Summary Iterations Tested Documented Acceptance SIZE DONE
size done size done size done
agiletracplugin
#44 TracAdmin should be able to install agile-trac onto an existing trac environment with predicable results. 13 18 8 3 5 16
#72 Color notation of status on Iterations and Roadmap is missing in IE and Safari 18 5 0 3 8
#79 Use labels for ticket stages in ticked new/edit menu 17 18 1 0 0 1
#80 Roadmap Error 18 0 0 0 0
agile-trac.org
#86  http://agile-trac.org does not work 18 1 0 0 1
#88 Allow to see Timeline + SVN changes 18 1 0 1 2
agiletrac patch to core
#82 TracAdmin should be able to use Agile-Trac with Trac 0.11.2 18 8 1 5 14
#85 MilestoneAdmin? can use a date picker to select a Due date for a milestone 18 1 0 1 2
#87 TracAdmin should be able to use Agile-Trac with Trac 0.11.3 18 5 1 3 9
completion stages
#47 EndUser? understand the effect of choosing 'fixed' as a Resolution for tickets after installing agile-trac 13 18 0 1 0 1
#84 TicketUser? can use a date picker to select completion stage progression dates 18 3 0 1 4
roadmap UI customisation
#89 EndUser? should be able to view tickets in the Roadmap view grouped by component 18 3 0 1 4
iterations
#61 EndUser? should be prevented from crashing agile-trac with empty iteration dates 12 14 18 5 1 1 7