Roadmap

Milestone Summary
Milestone Value to Deliver Due Date Expected Date Progress
Stories Points To Do % Overview
Patch Against Trac 0.11 16 151 0 Finished, no date was set Completed 07/22/2008 100%
Plugin with Patch against Trac 0.11 2 35 0 Finished, no date was set Completed 08/04/2008 100%
Clean up of Plugin with Patch 65 292 29 No date set Tue 28 May 19
Fri 19 Jul 19
90%
Better User Story Support 9 71 71 No date set Tue 03 Mar 20
Fri 08 May 20
0%
Near Term 8 118 118 No date set Mon 17 May 21
Mon 15 Nov 21
0%
Long Term 1 8 8 No date set Wed 04 Aug 21
Tue 17 Aug 21
0%
Based on 5.0 points per iteration with an average iteration length of approximately 20 days
points per day iteration
Note: See TracRoadmap for help on using the roadmap.